Wednesday, November 18, 2026


Romulus Trade Center expansion plan approved


A major expansion of the Romulus Trade Center is moving forward following final approval by members of the Romulus City Council, clearing the way for NorthPoint Development to proceed with plans for two large warehouse and distribution facilities totaling more than 856,000 square feet.

The council approved the special land use request Nov. 9, marking a significant milestone in the project that is expected to bring approximately 300 permanent jobs and generate an estimated $41 million in new taxable revenue for the city during the next 20 years.

The expansion will occupy approximately 108.48 acres north of Ecorse Road, in an area near Henry Ruff and Beverly roads. The property was conditionally rezoned from single-family residential and general business classifications to light industrial in May.

The development calls for two cross-dock warehouse facilities. The larger building will contain approximately 475,170 square feet, while the second will encompass about 381,090 square feet. An additional 4.5 acres has been designated for future mixed-use commercial development.

As part of the Nov. 9 meeting, council members also approved a resolution to vacate a portion of Henry Ruff Road north of Ecorse Road to accommodate the industrial development. The city will retain a permanent utility easement over the vacated roadway.

The project includes several commitments intended to provide benefits to the community and address concerns about the development's impact on surrounding neighborhoods.

NorthPoint Development has committed to a $300,000 community-benefit payment, along with an additional $62,235 payment in lieu of constructing a sidewalk along Beverly Road.

Plans also include a 550-foot setback from Beverly Road to provide separation between the industrial buildings and nearby residential properties. In addition, 15 percent of the mature tree canopy will be placed in a permanent conservation easement.

Traffic management is another significant component of the plan. Heavy truck traffic will be prohibited from using Beverly Road, with truck access directed to Ecorse Road. Improvements to Ecorse Road are planned, including widening and an 8-foot pedestrian path.

Environmental considerations also have been incorporated into the development. Approximately 23 acres of wetlands are located on the property, with about 3.9 acres expected to be disturbed and mitigated through on-site measures. The plan also calls for expanded capacity along the Black Creek drain to help address local flooding concerns.

The project has moved through several stages of municipal review. In May, the council adopted the conditional rezoning ordinance. The Romulus Planning Commission subsequently approved the site plan Sept. 21 by a 7-0 vote and recommended final approval of the special land use request.