Crews were expected to complete Phase II of the 2023 Central Parking Deck renovation project in downtown Plymouth last weekend.
Phase III of the project was expected to begin immediately and will require the closure of the entire upper level of the Central Parking Deck as preparations begin for the resurfacing of the upper level and the ramp. Work on Phase III is expected to take approximately one week, depending on weather conditions, officials said, and the entire upper level will remain closed during that time.
Motorists can park vehicles without time limits at the Christian Science Church located at 1100 W. Ann Arbor Trail. The Downtown Development Authority staff secured the area for additional public parking through the end of June.
Locations of additional municipal lots are available at: https://downtownplymouth.org/105/Maps. Enforcement of all other time limits will remain in place during this project, officials said.Once Phase III is complete, only a few minor repairs will remain with little to no impact on the parking system.
Crews are expected to return after Art in the Park weekend to make those minor repairs to complete the project
More information is available by email at dda@plymouthmi.gov.