Trash collection resumed the regular schedule on Avondale Road in Inkster last week as Phase One of the reconstruction of the road continues.

Dumpsters placed along side streets for the collection of trash during the construction were also scheduled to be removed, according to city officials. The project includes the reconstruction of Avondale between Henry Ruff and Eastern. Completion of the project, which began in March is expected this month.

As part of the project, a new concrete roadway was installed along with new sidewalks and accessible ramps. The project also included a new water main, a new storm sewer and repairs to the existing sanitary sewer.

Motorists have been detoured onto Henry Ruff, Cherry Hill and Inkster roads during the work.